Wu Jihan's mining company Bitdeer announced an update on its operations for October 2023. As of October 31st, the company's total managed hash rate (including self-mining, cloud mining, and hosting) reached 21.2 EH/s, with 462 BTC mined (only through self-mining). Among them, the Gedu data center in Bhutan provided 3.3 EH/s of hash rate and mined 211 BTC, accounting for 46% of the total BTC mined that month. The total power capacity of the six mining data centers remained stable, totaling 895 MW. In addition, the company has made progress in the 175 MW immersion cooling data center in Norway, which is expected to be completed in 2025.